ClockSunday, 05/07/2026 12:44

Berth No.4 of Chan May Port to Come Into Operation in Early September 2026

HNN.VN - This was the information announced on the morning of July 4 by Mr. Tran Dinh Quoc, Supervising Engineer at VSICO Maritime JSC (VSICO), the investor of Chan May Port Berths No.4 and No.5 General Cargo and Container Terminal Project.

38,000 visitors arrive in Lang Co during the event honoring the world beautiful bayNearly 1,400 runners take part in the Chan May - Lang Co running race 2026Ensuring tourism environment during the “Lang Co - World Beautiful Bay” programReviewing and Inspecting Project Progress at Chan May - Lang Co Economic ZoneConstruction begins on social housing project in Chan May

 Workers are racing to complete the construction of Berth No.4

According to Mr. Tran Dinh Quoc, several key components of Chan May Port Berths No. 4 and 5 General Cargo and Container Terminal Project have made significant progress.

At Berth N0.4, construction of the temporary Geotube seawall, installation of prefabricated vertical drains, ground reclamation, and dredging of the berth basin have all been completed. All 500 foundation piles for the wharf have been driven. Meanwhile, all 1,077 precast concrete components have been manufactured, with 786 units installed, representing 73% of the total construction. Furthermore, construction of the wharf deck has reached 4,500 m2 out of 10,800 m2, reaching about 45% of the planned volume.

Production of the two multipurpose quay cranes has also been completed, while construction of the yard foundation and drainage system is progressing simultaneously. Under the project schedule, Berth 4 is expected to be completed and come into operation on September 10.

Also being developed by VSICO JSC, Berth No.5 has so far completed the installation of 6 test piles and the fabrication of 17 out of 374 precast girders, equivalent to 4.5% of the planned volume. However, large-scale construction has yet to commence due to unresolved site clearance issues involving an underground petroleum pipeline serving the Chan May Fuel Depot operated by PVOIL, as well as the navigation channel used by fishing vessels on the Lach Giang River.

VSICO JSC has called on the Management Board of the Economic and Industrial Zones and Hue City People’s Committee to step in and support the contractor in hastening the project’s implementation so that it can be completed and put into operation in October 2028.

Implementing night-time construction to speed up the completion of the access road to Chan May Port’s Berth No.4 

Chan May Port Berths No. 4 and No. 5 General Cargo and Container Terminal Project received investment policy approval from the Management Board of Hue City’s Economic and Industrial Zones under Decision No. 161/QD-KKTCN, dated October 6, 2022.

The project has a total investment of over VND 1.678 trillion and covers an area of 20.4 hectares. Under the approved design, the two berths will have a combined length of 540 meters and will be equipped with wharf infrastructure, warehouses, storage yards, technical infrastructure, machinery and equipment to provide cargo handling, warehousing… Once completed, the facilities will be capable of accommodating general cargo vessels of up to 70,000 deadweight tons and container ships of up to 4,000 TEUs.

By Minh Van
RATING
Be the first to review this post!
  Comment

YOU MAY CARE ABOUT

Chan May toward a green seaport

Developing green seaports is an inevitable tendency, aiming at meeting international environmental standards, enhancing competitiveness, and maintaining sustainable development.

Chan May toward a green seaport
Seeking Solutions to Boost Export Growth

On the afternoon of July 23, the Department of Industry and Trade held a conference to discuss measures to boost export growth in 2026 and achieve the city’s export target, contributing to the implementation of the city’s goal of recording GRDP of over 10%.

Seeking Solutions to Boost Export Growth
Racing against time

Standing at either end of Truong Tien Bridge at the moment, we witness construction barriers having been erected, vehicles temporarily halted, and the bridge is handed over to crews working through the night.

Racing against time
Hue Today, Issue No. 474, published on July 16, 2026, is now Available

Hue Today No. 474 features a range of notable stories, including the city’s regular citizen reception program, the training of doctors for mountainous areas, ongoing DNA sampling to identify fallen soldiers, and a talk show by a professor with students on the enduring love for the ao-dai.

Hue Today, Issue No 474, published on July 16, 2026, is now Available

LASTEST NEWS

Return to top