Outdoor stage at Quoc Hoc Stele area to be completed before March 25th

HNN.VN - To ensure timely service for the opening ceremony of the National Tourism Year - Hue 2025, scheduled for the evening of March 25th, Thuan Hoa District Green Park Center is accelerating the construction of an outdoor stage along the southern bank of the Huong River. The project is set to be completed and handed over by March 20th.

Launching the video National Tourism Year - Hue 2025Many hopes for the National Tourism Year - Hue 2025

 Construction teams are mobilizing all resources to complete the outdoor stage before March 25th.

Due to the tight schedule, construction teams are working at full capacity, deploying dozens of machines and equipment, with 30 - 40 workers per day operating in three shifts to ensure completion as planned. The stage is designed in a crescent shape, with a 3,000m² audience area, featuring 334 meters of solid stone seating and seasonal grass and flower plantings. Additionally, floodlights, embedded LED lights, and waterproof LED strips are being rapidly installed.

 Rendering of the outdoor stage for the opening night of the National Tourism Year.

This project is one of the largest-scale investments in Thuan Hoa District in 2025, with a total investment of 28.5 billion VND. It aims to enhance the landscape and maximize the tourism potential of both banks of the Huong River, providing a new recreational space and a venue for major events in Hue City.

By THANH HUONG
RATING
Be the first to review this post!
  Comment

YOU MAY CARE ABOUT

“Overtime and extra shifts” at construction sites of inter-level schools in A Luoi communes

On the morning of April 15th, Mr. Nguyen Dinh Trung, Member of the Party Central Committee, Secretary of the City Party Committee, and Head of the city’s National Assembly Deputies Delegation, along with a working delegation, inspected the progress of investment and construction of primary and lower secondary boarding inter-level schools (inter-level schools, for short) in A Luoi 3 and A Luoi 4 communes.

“Overtime and extra shifts” at construction sites of inter-level schools in A Luoi communes
Construction begins on Vlasta Premier - Phu Hoi Project

On the morning of March 29th, in Thuan Hoa ward, Hue City, Van Phu Real Estate Development Joint Stock Company (project developer) and Union Success Vietnam Joint Stock Company (investor) held the groundbreaking ceremony for the Vlasta Premier - Phu Hoi Project (technical infrastructure component).

Construction begins on Vlasta Premier - Phu Hoi Project
Construction begins on social housing project in Chan May

On the morning of March 26th, in Chan May - Lang Co Commune (Hue City), FUTA Land Real Estate Joint Stock Company held the groundbreaking ceremony for Chan May Social Housing Project (located in Chan May Urban Area, Lot No. 8). The event was held to mark the 51st anniversary of Hue Liberation Day (March 26th, 1975 - March 26th, 2026).

Construction begins on social housing project in Chan May

LASTEST NEWS

Return to top