Most components have been completed. Photo: N.L

Opened to traffic in 2022, the 65-kilometer La Son-Hoa Lien Expressway connecting Hue and Danang initially had only two lanes, with traffic in opposite directions largely separated by painted road markings. The route begins at its junction with Cam Lo-La Son Expressway in Hung Loc Commune (Hue City), and ends at its junction with Hoa Lien-Tuy Loan Expressway in Lien Chieu Ward (Danang City).

After over a year of construction and expansion work, La Son - Hoa Lien Expressway now features a four-lane roadway along its route. Compared with its original two-lane design when it opened to traffic in April 2022, the expressway has undergone a significant transformation, improving traffic capacity and road safety conditions.

The asphalt concrete roadway has been widened, with opposing traffic flows now separated by the rigid median barriers. Road markings, traffic signs, metal highway guardrails, and anti-glare screens have also been installed at various locations, contributing to guiding traffic and reducing the risk of head-on collisions along the expressway with challenging terrain.

While the road widening work has largely been completed, several components of the project still require further attention. One notable issue is the relocation of Khe Tre interchange in Hue City, as the original site was found to pose safety risks. The new interchange is being moved to Km 14+960, one kilometer away from its former location, to connect the expressway to Provincial Road 14B and ensure convenient travel for residents. According to survey results, the new site has flatter terrain and more stable ground conditions, helping minimize the risk of landslides previously reported at the old interchange at Km 13+250.

Mr. Tran Duc Hiep, Director of La Son - Hoa Lien Expressway Expansion Project Management Board, informed that site clearance for construction of the new interchange affected five households, and all required land has now been handed over. However, construction progress remains under pressure as work is still awaiting the relocation of four 22 kV medium-voltage power poles, a D90 clean water pipeline, and the telecommunications cable system.

With a tight construction schedule coinciding with the peak rainy and flood season, contractors are accelerating work on the new interchange. To date, more than 90% of the drainage works have been completed, while roadbed excavation and embankment have reached over 20%. Construction plans must also account for surface water drainage to minimize the impact of prolonged heavy rain.

“To proactively address the risk of landslides and ensure traffic safety during the rainy and stormy season while the old interchange remains operational, the Management Board of the project has instructed the contractor to prepare a plan for temporary access and exit ramps at the new interchange. Essential materials have already been stockpiled and are ready for the construction of a temporary road in case of an emergency. Under the plan, the remaining works along the expressway are expected to be completed before December 31, 2026,” said Mr. Hiep.

The following are a series of photos taken by Hue Today Online on the four-lane expressway running through Bach Ma forest:

The road offers an impressive scene with several curvy sections running through the forested mountains. Photo: N. L 
Several landslide-affected sections along the route have been repaired and restored. Photo: N.L 
 Most of the project works have been completed. Photo: C. Tuan
Four of the five drainage culvert components have been completed. Photo: C. Tuan 
 Work on several additional items is progressing rapidly. Photo: C. Tuan
Relevant agencies are urgently relocating power poles from the project area. Photo: C. Tuan 
 Taking advantage of favorable weather conditions, construction teams are accelerating work on the project. Photo: C. Tuan
By Cong Tuan